Price score
Korea's 2026 second-half offshore wind auction scores price out of 50 points. The notice sets the score at 50 minus 1.25 points for every percentage point by which the bid exceeds 85% of the ceiling price, and any bid below 85% is scored as if it were at 85%.
The fixed-bottom ceiling is 168,937 KRW/MWh on the mainland and 168,913 KRW/MWh on Jeju, and KWI uses the mainland value throughout. The formula gives 31.25 points for a bid at the ceiling and 50 for a bid at 85% of the ceiling, so price can separate two bidders by at most 18.75 points. The bid price for full price marks is 143,596 KRW/MWh.
The bid combines the electricity price, called SMP, and the price of one renewable energy certificate (REC) into a single price per MWh. The reference SMP is 86,350 KRW/MWh. After selection the fixed contract price is the reference SMP plus the bid's excess over SMP multiplied by the project's REC multiplier. The contract runs 20 years in principle.
The break-even bid is the lowest bid at which a project recovers its modelled cost, including a 10% return, in KWI's model.
Once a break-even bid qualifies for full price marks, further reductions add no points.
The auction has a general market of about 1,400 MW and a public-led market of about 300 MW for fixed-bottom projects. The preference is excluded from the submitted bid and added only in the fixed-price formula, so it does not enter the price-score formula directly. On KWI’s calculation, the basic public-led preference of 3,660 KRW/MWh lowers the break-even bid by that amount, equivalent to about 2.7 price points before the 50-point cap. An additional 27,840 KRW/MWh for R&D demonstration equipment can lower it further.
In short On KWI’s calculation using the notice formula, the maximum price-score difference is 18.75 points, and every bid at or below 85% of the ceiling receives 50 points.
Nine fixed-bottom projects, lettered A to I
The comparison covers nine fixed-bottom projects, labelled A to I. Eight have completed the main environmental impact consultation and can bid. The other remains in its main consultation, which will decide whether it can bid. Project-level values are KWI model estimates. Projects that have completed the main consultation are listed in KWI's earlier Deep Dive, Korea's 2026 H2 Offshore Wind Auction: 2.2 GW on Offer, 14 Projects Eligible.
The figure counts projects by capacity, water depth and foundation. Monopiles are usually chosen in shallower water and jackets in deeper water, and these construction-cost differences affect levelised cost.
Higher wind speeds mean more annual electricity generation, distributing the same project cost over more megawatt-hours. KWI's model puts mean wind speed at 150 m across the nine projects at about 7 to 8.5 m/s.
Differences in water depth, foundation type and wind speed lead to differences in cost across the nine projects.
In short The 9 projects compared by KWI differ in size, water depth and foundation type, so their costs differ too.
Levelised cost comparison by project
At P50, KWI's model puts the levelised cost of the most expensive project at about 1.4 times that of the cheapest. On an index with the median cost of the nine projects set to 100, the P50 values run from 92 to 131.
Levelised cost divides lifetime construction and operating costs by electricity output. The index compares the nine projects without disclosing actual costs.
P50 is the median cost case and P90 the conservative one. The P90 marks show how much each project's cost can rise. KWI's model keeps the same two most expensive projects in both cases, while the order of the others changes.
In short At the middle cost estimate, KWI puts the most expensive project at about 1.4 times the cost of the cheapest.
From cost to bid price under the REC multiplier
The multiplier works on the part of the bid above the reference SMP. A multiplier of 3 means the developer receives 3 times that part of its bid as fixed price. To recover the same cost, that part of the bid needs to be only 1/3 as large. KWI uses the fixed contract price formula in the notice to calculate the bid price needed to recover each project's cost.
At the same cost, a higher multiplier lowers the break-even bid, increasing the likelihood of obtaining full price marks at or below 85% of the ceiling. Small multiplier changes can substantially change bids, especially for expensive projects with wider cost-to-SMP gaps.
The multiplier depends on water depth and on the grid-connection distance measured from a coastline. KWI reads the rule as referring to the coastline of land connected to KEPCO's grid, or of islands connected to that grid from the mainland. The distance is measured only from the mainland and from islands whose connection to that grid appears in public data, and an island with no connection record is treated as not connected. Uninhabited islands, islands on their own generation and neighbouring islands supplied only by such islands are left out, so each project has one multiplier. This coastline basis follows that interpretation; KEA has not verified the resulting values for individual projects.
On that basis KWI's multipliers for the nine projects run from about 2.5 to 4.5 in increments of 0.25. They are estimates, and KEA has not confirmed them.
In short For the 9 projects compared by KWI, a higher REC multiplier allows the same cost to be recovered through a lower bid price.