100 MW project under construction with AWS, targeting initial operation in 2027
Nationwide expansion to 15 GW envisaged by 2035; securing power and major technology customers will be key
President Lee Jae-myung's visit to SK's artificial intelligence (AI) data center construction site in Ulsan on November 21 is drawing attention to SK Group's plan to build a nationwide network of large AI data centers with a combined capacity of 15 gigawatts (GW).
SK Group plans to expand AI infrastructure across five regions nationwide by 2035, starting with the Ulsan AI data center being built jointly with Amazon Web Services (AWS).
However, expanding the 100 megawatts (MW) currently under construction to gigawatt scale and realizing the long-term plan is expected to depend not only on securing extensive grid infrastructure and land but also on attracting global technology customers to underpin stable returns.