Skip to content

Nowhere for the Power to Go: Projects Cut to Five Years, Lines Still Thirteen

The Offshore Wind Special Act took effect on 26 March 2026. A project that took more than ten years on average is expected to take five or six. Laying a single transmission line still takes thirteen years, and the largest designated zones sit where new grid connection is closed.

Share:
Nowhere for the Power to Go: Projects Cut to Five Years, Lines Still Thirteen
Published:
01

The law is in force. The lines are not.

On 26 March 2026 the Act on the Promotion of Offshore Wind Deployment and Industrial Development took effect. Under it the government designates the sea area first and carries out the survey work, local government secures community acceptance, and a developer selected by auction then builds inside that area. This is the planned siting regime, and its purpose is to compress a permitting process that has taken more than seven years into thirty-one months.

That cleared one of the largest obstacles in Korean offshore wind. One question remains. When the turbines turn and the electricity is produced, where is it supposed to go?

On paper the preparation looks ample. The government has designated ten cluster zones totalling 14.4 GW. The 11th Basic Plan for Electricity Supply and Demand sets a 2030 offshore wind target of 10.5 GW and a 2035 target of 25 GW. What is actually turning today is 0.35 GW.

ItemCapacityReference
Designated cluster zones14.4 GWAs at March 2026, ten zones
2030 deployment target10.5 GW11th Basic Plan for Electricity Supply and Demand
2035 deployment target25 GW11th Basic Plan for Electricity Supply and Demand
In commercial operation0.35 GWEnd of 2025

Note. After the Ministry of Climate, Energy and Environment designated seven further zones on 15 March 2026 the total stood at nine schemes and roughly 13 GW. Taean at 1.4 GW brought it to ten zones and 14.4 GW. The figure includes the Jeonbuk southwest pilot zone at 0.4 GW and the diffusion zone at 1.0 GW. Source=KWI cluster zone status report, 11th Basic Plan for Electricity Supply and Demand

14.4 GW is designated. 0.35 GW is turning. That gap is not a rounding error.

Found this useful?

Share this article with your network.